Break Even Stripping Ratio (BESR)
November 16th, 2022
Given an underground total mining cost of $8.85 per tonne, surface mining costs of $2.95 per tonne of ore, and surface mining stripping costs of $1.75 per tonne of waste, calculate the break even stripping ratio (with zero profit) between surface and underground mining.